June 2023 – 46 Berwick Street, London – CAT A refurbishment, Project Instructed.
This project is a CAT A refurbishment of the existing ground and basement of the building, with extensive structural reinforcement works being carried out.
Works include white boxing the ground and basement to allow a blank canvas for potential tenants. This consists of decorations throughout, track lighting, opening up works and tanking the rear vault.
The rear ground floor space is being expanded by making use of the courtyard creating an inside space and opening it up with an architectural glazed roof.
Started June 2023, completed September 2023.
Client-
Project Manager-
M&E Consultant-
Cost Management-
Architect-
Structural Engineer-