October 2023 – 14-16 Hans Crescent, London – High End Residential refurbishment, Project commenced.
This project is a high end residential refurbishment of the top floor/s (duplex) apartment of the building to allow a future letting.
Works include replacement of roof coverings, new roof-lights, replacement windows, new partitions, plasterboard ceilings complete with feature detailing and cornicing, hardwood and stone floors, bespoke joinery including wardrobes; bathroom fitments; desks; general cupboards; feature doors; new high spec kitchen installation, specialist wall finishes, decorations, etc.
Electrical installations, mechanical and public health installations, Audio Visual Installations (integrated with M & E installations including lighting and heating controls etc) are also being installed.
Started August 2023, completion Due March 2024.